I am working in a project that has 3 different sub-projects. Two of them need to be in a 24-hours calendar and the other one has to be in a 8-calendar (standard).
Every time I merge them (either linking them automatically or copying and pasting) MS Project change dates and/or durations.
I read and followed the steps in the article
http://blogs.captechconsulting.com/blog/david-elliott/managing-multiple-calendars-microsoft-project but it's not working to me. I don't have resources assigned though.
Any ideas?
Many Thanks